Skip to main content

Grafton Waste Water Treatment Plant

Firm’s Responsibility:  General Contractor

Cost:  $3,200,000.00

Scope:  Phase 1 consisted of replacing the existing UV system, replacing/enlarging tertiary filter piping and distribution system, fine screen replacement and screen chamber modifications.

Phase 2 consisted of massive earthwork to construct a 5.1 million gallon concrete-lined EQ basin.

Phase 3 was full depth removal and reconstruction of the entrance road.

Self-Performed Services:  Process piping, earthwork, utilities, EQ basin, general construction

Contact Us

Please enable JavaScript in your browser to complete this form.
Thank you for your interest in Simonson Construction. To begin a conversation with us, please fill out the form below or call us at (419) 281-8299. Our main office is located at: 2112 Troy Rd., Ashland, Ohio 44805 View A Map »